OVERVIEW: Chemcote’s specialist team mobilised to site to deliver a multiple layer protective coating system that would return the asset to working condition within 24 hours. Abrasion resistant coatings were applied to the pugmill and paddles over a 12 hour period during plant shutdown, with 12 hours allocated for curing.
INDUSTRY
ENVIRONMENT
50-70°C 10-40μm abrasive particles from the dust catcher are disposed of in the pugmill and combined with water to suppress the dust creating an abrasive sludge
SUBSTRATE
Steel Substrate
CHALLENGE
Deliver an operational multi coat abrasion resistant coating system within 24 hours
SOLUTION
Thorough surface preparation prior to the application of multiple layers of abrasion resistant coatings. Spot abrasive blasting to minimise disruption to surrounding trades.
SCOPE
Pugmill Internals
Spot abrasive blast localised areas.
Apply of 1 coat of fast curing Chem-tect™ RB 364C to areas where required
Use chopped strands and where deep pitting existed to provide a smooth even profile
Apply 2 coats of Chem-tect™ RB 364CS to 1,000μm
Conduct QA, DFT and high voltage spark test to ensure continuity at required voltage
Paddles
Abrasive blast to AS 1627.4, Class 2.5 with a minimum 75μm profile.
Apply 1 coat of Epo-chem™ RW 500 to a nominal thickness of 500μm to ensure no transparent areas
Complete casting application 1 coat of InD-cote™ to 6000 micron DFT to the load and back faces
PRODUCTS
Paddles coated using Epo-chem™ RW 500 and InD-cote™
Pugmill Internals Chem-tect™ RB 364CS
OUTCOME
Chemcote’s solution has extended the life of this asset by 12-24 months, and delivered a 30% improvement in functioning. Continuous high performance is guaranteed until our review at the next planned outage.
RELATED CASE STUDIES
Centrifugal Pump Corrosion Protection
Before Coating Application Strip & Assess Kevlar Application anti swirl vane Applying the 1st Coating Completed Internal Coating application OVERVIEW: Chemcote provided a long-lasting solution
Maximise Pipe Durability Using Composites
Condition Before Coating Coating to critical areas complete External coating carried out on site Externals Requiring Relining OVERVIEW: Chemcote was tasked with extending the service
Refurbishment of Basket Strainer
Strainer nearing completion Internals nearing completion Internals illustrating pit filling After abrasive blasting, pitting After fabrication repairs OVERVIEW: Chemcote provided a long term corrosion protection for