OVERVIEW: Highly corroded carbon steel decks would have taken 12 months to re-surface with riding crew permanently on board. Corrosion would have re-appeared upon completion under high humidity and rain conditions. Chemcote applied wet & surface tolerant coatings with minimal disruption to the everyday activities
INDUSTRY
ENVIRONMENT
Hot and humid, sea mist
SUBSTRATE
Structural Steel
CHALLENGE
Highly corroded carbon steel decks would have taken 12 months to re-surface with riding crew permanently on board. Corrosion would have re-appeared upon completion under high humidity and rain conditions.
SOLUTION
Chemcote’s application of wet & surface tolerant coatings was carried out with minimal disruption to the everyday activities and came with a 10 year warranty, much to the rig manager and asset owner’s satisfaction
SCOPE
15,000 – 19,000 psi water blast with small footprint machine
Wet abrasive blasting to reduce metallic salt content
Perforations were found in accommodation quarters and other critical areas
Applied 1 coat RS 500P and laminated using 600gm/m2 multi-directional matting
Applied 1 coat RA 500M with a nominal thickness of 500μm—700μm
PRODUCTS
OUTCOME
Application was complete within client’s time frame, and asset owner also saved 12 months of downtime and repetitive painting costs. Chemcote has been awarded continuous work on the rest of the problem areas and other rigs from the same client.
RELATED CASE STUDIES
Blast Furnace Recovery Turbine Repairs
Set up of Containment Masking before Blasting Spool Condition before Coating Aerial view of Outlet Spool from Shutoff Valve Completed Outlet Spool Internals Application of
Long Term Protection Of ISOtainers
Newly fabricated tank internals Tank Internals Confined space entry Completed tanks for delivery to customer OVERVIEW: The asset owner approached us to provide protection
Floating Restaurant Structure Repairs Using Underwater Curing Epoxies
Condition before surface preparation Mechanical Preparation Primer Application Second Coat applied OVERVIEW: In the complete refurbishment of the underside of this floating structure, some