Relining of Open Top Quench Tank
Condition before abrasive blasting Containment set up to prevent dust emissions Removal of garnet after abrasive blasting First Coat Spray applied OVERVIEW: Chemcote’s specialist
View over 100 detailed case studies by industry.
Condition before abrasive blasting Containment set up to prevent dust emissions Removal of garnet after abrasive blasting First Coat Spray applied OVERVIEW: Chemcote’s specialist
Site set up Condition upon inspection After Blasting Coating Complete OVERVIEW: When you’re storing harsh chemicals like sulphonic acid, unfortunately deterioration, staining, and corrosion
Needle Gunning to minimise Abrasive Blasting Costs First coat applied after abrasive blasting Pitfilling to ensure coating continuity Reassembly on site OVERVIEW: Illustrated a
Severe pitting after 2 months in service After abrasive blasting Damaged internals rebuilt and coated Externally applied caution OVERVIEW: New 316L pipe failed after
Newly constructed bund Primer application Application of final coat Job completed OVERVIEW: Chemcote was contracted to apply acid protection to a newly constructed delivery
Flange is barely attached Repairs commence Repairs using composite weave mat Coating complete OVERVIEW: A power station client required corrosion protection for a 30-plus